Building Project Timeline
*Events will be added as they occur.*
 
2012
August 2012 - School board approves official name as Philipsburg-Osceola Area Middle School.
 
July 2012 - Construction begins!
 
2011
Fall 2011 and Winter 2012: P-O works with Fourth Economy to explore reuse options for the Junior High School Building. Mutiple community meetings are held with local stakeholders to discuss the options.  
 
November 9, 2011: Middle School Education Specifications presented to the board and public.
 
February 8, 2011: Elementary capacity study presented to the board and public.
 
March 1, 2011: Board holds public interviews for architect.
 
March 8, 2011: Stantec, formerly Burt Hill, hired as the architectural firm for the project.
 
2008-2010
 
December 2008: Feasibility Study Completed by Architects Crabtree, Rohrbaugh & Associates.
 
October 26, 2009: At a school board meeting, Facilities Director Don Blake presents an overview of renovation needs as described in the feasbility study.
        Click here to read the State-of-the-Physical Plant handout given to the public at the meeting.
 
October 26, 2009: Community members are invited to join building committee.
      Click here to read the Centre Daily Times story.
 
November 16, 2009: School Board approves 23 members to serve on the committee. 
 
November 18, 2009: First Building Committee meeting. Group reviews building options and divides into subcommittees to begin studying the options in greater detail.
       Click here to read the meeting notes.
 
December 15, 2009: Second Building Committee meeting. Subcommittees present pros and cons of 5-, 4- and 3-building plans.
          Click here to read the meeting notes.
          Click here to read The Progress News story.
 
January 12, 2010: Public Forum at school board meeting, 7 p.m. at the North Lincoln Hill Elementary multipurpose room. Does the community support a 5, 4 or 3 school building renovation plan?
       Click here to read the meeting notes.
         Click here to read The Progress News story. 
         Click here to read The Centre Daily Times story.

January 26, 2010: Public Forum #2 at 7 p.m. at the Junior High School auditorium. Does the community support a 5, 4 or 3 school building renovation plan?   
         Click here to read the meeting notes.
         Click here to read The Centre Daily Times
story.

February 3, 2010: Third Building Committee meeting. Discussion of upcoming survey, public forums and moving forward.
        Click here to read the meeting notes.
           Click here to read the Centre Daily Times
story.

February 15, 2010: Deadline for the public to return completed community surveys.

March 3, 2010: Fourth Building Committee meeting. Community survey results are reviewed.

March 9, 2010: Community survey results are presented to the school board. 
         Click here to read the Centre Daily Times story, the Progress News story and the WJAC TV  
             report.
 
March 11, 2010:  Fifth Building Committee meeting. Committee picks 4-building option.
        Click here to read the meeting notes.
 
March 22, 2010: Building Committee recommends 4-building option to the school board during its public meeting.
        Click here to see the powerpoint presentation and the Progress News story.
 
April 13, 2010: Board approves 4-building option and approves a middle school at the North Lincoln Hill Elementary site.
 
Summer 2010: Board holds public interviews in search of consultant to develop Education Specifications.
 
August 10, 2010: Board approves Ingraham Dancu Associates to develop Education Specifications.

 